Will Man United’s new stadium be ready for the 2035 World Cup?
If recent precedents are anything to go by, an almost nine-year window between now and the tournament should be plenty of time to deliver Old Trafford’s 100,000-capacity replacement, even accounting for delays.
FIFA confirmed yesterday that the UK would host the Women’s World Cup in 2035, having been the only nation to bid. It is anticipated that the tournament will provide a £2.2bn economic boost to the UK economy.
The shortlisted venues were also confirmed, with Everton’s Hill Dickinson Stadium, Wrexham’s Racecourse, and the grounds of both Manchester clubs named as the North West hosts among the 22-strong list.
In Manchester United’s case, both the existing Old Trafford and the proposed replacement have been confirmed as potential venues.
Omar Berrada, chief executive at Manchester United, said: “Manchester United is proud to support the bid and excited by the prospect of playing a role in such a historic event.
“With our plans for a new 100,000-seat stadium, we are creating a football-first venue designed for the biggest moments in global sport. Hosting Women’s World Cup matches in our new stadium would be a fitting way to showcase Manchester and the women’s game on the world’s biggest stage.”
If recent precedents are taken into account, an almost nine-year runway provides plenty of time for the club to get the project finished comfortably in time for the World Cup, even accounting for some delays.
Everton’s Hill Dickinson Stadium, the last major English football stadium to complete, took a little over three years to build from the point at which planning approval was granted.
The same can be said of Tottenham Hotspur’s eponymous North London stadium, which ended up costing around £1bn.
Arsenal’s Emirates, which completed in 2006, took less than three years to build but five years passed between planning approval and handover, due to delays around financing.
The So-Fi Stadium in California, which is the most expensive sports venue ever built, took around four years to complete. The stadium, home to the LA Rams and LA Chargers NFL franchises, cost around £4.2bn to construct.
Manchester United’s proposed new stadium will be the largest and most expensive football ground ever delivered in the UK so it is reasonable to assume a longer construction programme.
The club and Prime Minister Andy Burnham have previously stated that the aim is for the new ground to be ready in time for the 2035 Women’s World Cup.
A planning application is expected within the next 12 months. Subject to approval within a year, work could begin by 2029. Even a five-year build – two more than both Everton and Spurs’ schemes – would see the stadium complete some time in 2034.
Working in United’s favour is the fact the club already has the land secured and early-stage design work with architect Foster + Partners is underway. In addition, the area where the new ground is to be located is under the purview of a Mayoral Development Corporation, a vehicle that has powers around land assembly.