Cumbria Combined Authority will vote next week to plug a funding gap for the University of Cumbria’s transformation of the historic site, which would see the building of 86,100 sq ft of teaching and support space.
If the grant of £1.4m is agreed, main contractor GRAHAM could start construction on the scheme in December.
The money would come from Cumbria Combined Authority’s Mayoral Investment Fund and would be divvied out over the course of three financial years.
The project focuses on creating a city centre campus for the University of Cumbria. This would sit on the four-acre Citadels site off English Street in the heart of Carlisle. In addition to creating teaching space, there would also be a 8,600 sq ft Carlisle Business Exchange developed – a start-up hub with coworking and flex office space.
CCA’s vote to award funding for the scheme comes just months after Cumberland Council decided to issue a £12m loan to get construction moving.
Most of the £84.2m project’s funding comes from the Borderlands Inclusive Growth Deal, which is contributing £62.1m to the effort. The University of Cumbria is chipping in £15.5m and a further £5.2m is coming from the Carlisle Town Deal.
The project has been nearly a decade in the making, as it was first conceived in 2018. It’s first full business case was approved in September 2021, with a second business case with a reduced scope agreed in October this year.
If construction can begin in December, the campus should be on track to complete in August 2028. When it opens, the University of Cumbria projects that it will increase weekly footfall in the city centre by 11,300 and bring in 1,060 additional full-time students.
The project team includes DAY, DPP, Curtins, and Urban Green. You can learn more by searching reference 22/0261 on Cumberland Council’s planning portal.