Salix presses ahead with latest phase of £55m Salford remediation
Eight tower blocks across the city are to have their non-complaint external systems replaced as the housing provider seeks to bring its assets in line with the Building Safety Act.
Salix Homes has submitted plans to remediate Black Friar Court, Newbank Tower, and Riverbank Tower in Trinity ward and Floral Court and Cheshill Court in Broughton.
The buildings were last upgraded between nine and 13 years ago but new legislation following the Grenfell tragedy means some of the materials used in the most recent refurbs are no longer compliant with legislation.
Salix has been actively improving its buildings in the name of resident safety in recent years and is nearing completion on a similar package of works at White Friar Court and Grey Friar Court next to Black Friar.
Three more towers in Pendelton – Magnolia Court, Mulberry Court, and Sycamore Court – also need remediating.
The three tower blocks underwent a £7m transformation around a decade ago, followed by a cladding remediation programme completed in 2019, when the ACM panels were removed. Plans to replace the panels are expected to be submitted to Salford City Council early next year.
Salix Homes has appointed Michael Dyson Associates as architect and lead consultant to help develop the proposed improvements. The housing association has also secured £3.34m from Homes England to support the development of plans for five of the eight blocks.
Contractors are expected to be appointed in early 2027 and work could begin after the summer subject to sign-off by the Building Safety Regulator.
Glenn Martin, director of investment, development, and sustainability at Salix Homes, said: “Salix Homes is planning a major programme of investment across our tower blocks in Salford, demonstrating our ongoing commitment to improving building safety and investing in the long-term future of our high-rise buildings.
“Building safety remains at the heart of this investment. Through the government’s Cladding Safety Scheme, we’re progressing plans for remediation works at eight of our tower blocks, alongside wider investment work to improve energy efficiency and modernise our buildings.”
Martin added: “We’re committed to continuing to invest in our tower blocks for the future, delivering lasting improvements that will benefit our customers for years to come.”