Developers face injunction over incomplete work in Blackburn
A High Court judge has granted an injunction against the companies behind delivering the 71-home Meadowbrook Rise off Haslingden Road, with the defendants also ordered to pay the local authority’s £122,200 legal fees.
Blackburn with Darwen Council took Walbury Homes, Walbury Commercial, Heron Homes, Adam Robinson, Katie Louise Irvine, and Peter Kiely to court over the work not done at Meadowbrook Rise.
The injunction will require them to complete within nine months:
- validation reports for all 67 of the completed homes regarding the safety of the land
- build a three-metre-high earth bund to address noise concerns
- complete road junction linking to Haslingden Road
- plant trees and install fencing as per planning agreements
- complete a play area
- complete required ecological habitats
None of the defendants attended the hearing, according to the council. However, if they do not comply with the court’s orders, they can face another round of financial penalties, imprisonment, or the seizure of their assets.
Heron Homes and Southworth Construction built Meadowbrook Rise. Southworth Construction was dissolved in February, according to Companies House data. Heron Homes faced a compulsory strike-off in May, but had the action was suspended a month later.
Heron Homes’ is run by director Joe Hindle, and formerly counted Irvine and Kiely as senior members of its team.
The same is the case for Walbury Homes, except Robinson was a director here rather than Kiely. Kiely is also a director at Walbury Commercial, which is currently in administration. A strike-off notice was issued for Walbury Homes in October.
This is not the first time Blackburn Council has taken legal action against the Meadowbrook Rise developers. It fined Heron Homes £24,600 earlier this year over the waste on the site.
Cllr Quesir Mahmood, deputy leader of Blackburn with Darwen Council, said: “We share the concerns and frustrations of our residents living at Meadowbrook Rise and have been working hard for many years to help try and support them in this difficult situation.
“From the outset, we’ve been clear that our powers as a council are unfortunately limited because this is a private development. However, that hasn’t stopped us from pursuing action wherever we are able to do so, and this injunction is an important next step.
“This injunction specifically links to planning breaches and gives us the backing of the High Court, placing clear, legally enforceable requirements on the developers to complete outstanding works and address issues that have been unresolved for far too long.”