Menai bridge repairs delayed by at least six months
Previously undetected water ingress on the underdeck steelwork of the suspension bridge has led contractor UK Highways A55 to push back the completion date from spring 2027 to autumn – a move that deputy minister for transport Mark Hooper said only confirms the need for a third crossing.
The Menai Suspension Bridge is 200 years old and the country’s first iron suspension bridge. It provides a vital link between Anglesey and Gwynedd over the Menai Strait, alongside the Britannia Bridge.
Work started on repairing the structure in September 2023. Since then, it has been hit with multiple delays, having first had a completion date of January 2026 that has been systematically rolled back.
Throughout much of this time, the bridge has had a 7.5-tonne weight limit
Hooper was far from pleased by the latest setback.
“I was extremely disappointed and frustrated to learn from the contractors that their programme of repairs, which has been beset by numerous delays, will be delayed once again,” he said.
“I have made it clear to UK Highways A55 Ltd since taking on this role the importance of maintaining momentum and providing confidence in the delivery programme, so this latest delay is unacceptable,” he continued.
“I recognise that a project of this nature can encounter unforeseen challenges and that safety must remain paramount, but I need to fully understand what steps are being taken to address the underlying issues.”
Hooper added that he had written to the chief executive of Equitix, UK Highways A55’s parent company to request a meeting to discuss the bridge.
The Welsh Government committed to delivering a third Menai crossing in October.