The heritage building's upgrade as designed by Purcell Architects. Credit: Purcell

Town Hall refurb cost ‘could overrun’

Upgrading Manchester’s grade one-listed town hall could cost an extra £17m due to economic volatility and the rising cost of building materials, the council said.

The Our Town Hall project is 50% complete and scheduled to finish in 2024. While “excellent progress” has been made since work began on site in July 2020, the project faces multiple risks that could negatively impact both the construction timeframe and the budget, Manchester City Council warned in a report to be examined by the Resources and Governance Scrutiny Committee on 11 October.

“The volatile economic climate – especially as it is affecting the construction industry where inflation is particularly severe – allied with the impacts of ‘discoveries’ as work progresses, mean the budget for this highly complex project is under significant pressure,” the report said.

“Sophisticated computer modelling shows that if 100% of the potential risks occur, the realistic worst-case scenario would be a £17m overspend – equivalent to around 5% of the overall budget.”

The £320m council-led project includes the full restoration of parts of the Alfred Waterhouse-designed building including the Great Hall, together with refurbishment and reparation of the building’s external fabric, windows, and roof.

Accessibility improvements are also planned, together with the creation of a visitor centre within the town hall and external public realm works. The town hall was built in 1868. Planning consent for the refurbishment was awarded in January 2020.

Manchester City Council noted in its report that overall materials prices across the construction industry went up by 44.1% between July 2020 and June 2022, and the sector faced acute labour shortages, too.

In addition, the “unique nature” of the Our Town Hall project has meant that challenges additional to those identified in pre-construction surveys are being discovered as the project team accesses and uncovers different parts of the fabric of the building.

“In some cases, this means more extensive work is required than originally anticipated,” the city council said, pointing to crumbling stonework, guttering and pipes, and other unforeseen issues.

For now, “no further funding is being requested at this stage and the project team are working tirelessly to mitigate against challenges and reduce any potential amount”, Manchester City Council said in its report.

Almost £4m of savings have been identified within the project, and any potential budget increase could be partly met through contingency funding for inflation impacts set aside in the council’s capital budget, it added.

“Risks are being constantly assessed and addressed, but with only around half of the construction phase complete there is still a long way to go.”

Lendlease is the main contractor, and the project team also includes Purcell as architect, Mace as project manager, Ramboll as structural engineer, Planit IE as landscape architect, Arup as building services engineer, and Faithful + Gould as quantity surveyor.

Manchester’s executive member for finance, Cllr Rabnawaz Akbar, said: “The project team have kept a tight grip on everything but in a period of exceptionally high inflation and considerable market volatility it’s important that we’re clear-sighted on the budget pressures and the work which is being done to minimise them.”

Deputy leader Cllr Luthfur Rahman added: “This is the biggest heritage project currently underway in the UK and will provide a remarkable legacy for Manchester – improving public access to this remarkable building and its artefacts and safeguarding it for future generations. It will also help many Mancunians into careers in construction.”

Your Comments

Read our comments policy

Worth it

By Anonymous

“The town hall was built in 1868. Planning consent was awarded in January 2020.”
So town planning decision-making is a lot faster now.

By Anonymous

    Thank you – we have now clarified that this consent relates to the refurbishment, not the building’s original construction!

    By Sarah Townsend

£320M is a bargain. we could get one and half Factory’s for that.

By Abel Wilson

The cost of everything is going up so all projects are going to over run what was projected prior to covid and ukraine.

It’s well worth it, we just need to make sure it’s the best job and as efficient as possible. Letting it rot isn’t an option and would only lead to bigger costs later.

By Anonymous

Pocket change compared to what is being spent on The Factory. The Town Hall will be still here in 100 years as well, so well worth the extra cost.

By Steve

Money well spent. Together with the reconstruction and enlargement of Albert square the civic quarter will look amazing when completed.

By John

It’s going to be fabulous. Unavoidable given the current goings on.

By Tom

5% overspend in the grand scheme of things with no contingency budget (as everything is fully costed) is not bad considering you would normally make an allowance of 15-20% contingency on a heritage project….

“sophisticated computer modelling”… is this a rebrand of Microsoft Excel?

By Anonymous

Hardly the Empire State Building is it?

By Dev

These heritage buildings are notoriously unpredictable (anyone that has refurbished an old house knows that!) When you consider the rising costs of everything now, this shouldn’t surprise anyone.

By Bob

Dev , what a strange comment, no it’s not, that’s in New York. If your point is that they shouldn’t spend all of that money on what’s recognised as one of the finest civic buildings in the county then you’ll need to be a little clearer in illuminating us all with your objection.

By Anonymous

@ Dev
Arguably the greatest town hall in the UK and one of the finest examples of Victorian/neogothic architecture in the world. UK town halls are hardly comparable to the Empire State Building, but I’m pretty sure this is an architectural blessing for Manchester.

By Anonymous

Worth every single penny

By Thankful

The Empire State building is iconic but not beautiful.

By Anonymous

If it speeds up the planning process and cuts red tape i’m all for it!

By Anonymous

Related Articles

Sign up to receive the Place Daily Briefing

Join more than 13,000 property professionals and receive your free daily round-up of built environment news direct to your inbox

Subscribe

Join more than 13,000 property professionals and sign up to receive your free daily round-up of built environment news direct to your inbox.

By subscribing, you are agreeing to our Terms & Conditions and Privacy Policy.

"*" indicates required fields

Your Job Field*
Other regional Publications - select below