The station is located close to both New Bailey and Greengate. Credit: via archive

Salford Central station upgrades delayed again

Works to improve Salford Central station, including improvements to existing facilities and extending platforms to improve capacity, may not begin until 2019, according to a report to the Greater Manchester Combined Authority.

The works on the station were due to be carried out in three phases; Phase 1a, which includes enhancements to both platforms and improvements to its canopy; Phase 1b, which includes a feasibility study into accommodating longer trains at the station; and Phase 2, which will bring back platforms three, four, and five back into use.

Phase 1a was to the first set of works to be completed, and TfGM originally said this would be finished by the end of 2017. This was then pushed back further last year, and TfGM said in September 2017 that works were likely to begin this year.

The project would have been carried out under Network Rail’s CP5 works package, which runs until the end of March next year.

However, Network Rail has now moved Phase 1a into its next works package, CP6, which begins in April 2019 and runs until March 2024, according to a report to the GMCA.

Following the delay, Transport for Greater Manchester said it was “in discussions with Network Rail with a view to exploring the options for delivering these enhancements at the earliest possible opportunity”.

A feasibility study for Phase 1b began in August 2017 and is due to complete in March 2018. This will look at options for accommodating longer trains at the station by March 2021.

However, this would not include lengthening the platforms, following an agreement with Network Rail and Northern. Any extension of the existing platforms will be part of the ongoing Network Rail North of England Route Study.

An expansion of Salford Central has been mooted since £20.5m of Growth Deal funding was allocated for the project in March 2014. A review at the end of 2014 by Network Rail found that the emerging design for the Ordsall Chord would mean that Salford Central could only accommodate four-car trains.

TfGM had thought it would be able to serve six-car trains at the station but the final design for Ordsall Chord, which was still going through legal and planning challenges in 2014, meant changes to signalling and track position.

In 2016, TfGM said it would have to find an additional £20m to carry out any extension of the platforms, and chief executive Jon Lamonte said the options for modernising the station presented “operational, timetable and financial challenges”.

Your Comments

Read our comments policy

If Salford was in Greater London rather than Greater Manchester it would get done NOW!

By JGW905

Wow, is Salford central really that important with Victoria only a stones throw away?

By Adam Ash

We can’t get basic platforms and station upgrades, yet London have new lines, trains, stations and a whole 2 new underground lines and masses, loads of stations costing billions done and agreed at a drop of a hat. We’ve all paid taxes to build infrastructure for the public to use, not all to be spent in London. The north councillors need to grow a back bone and demand the money for upgrades and work we all deserve and need! And given though Manchester’s economy is the largest in the north, why we can’t get money to fund projects like this is beyond me! Stop lending loans out to property for oversees residence only and help locals here in your local towns & cities!

By Northernlad

Northernlad is right.London Bridge station had a billion pounds of taxpayers money thrown at it. They get more on a station than we get on trainlines. The North contributes over 300 billion a year to our economy which is about 20 per cent of our total output. Do we get 20 per cent of infrastructure investment? Nowhere near.We can only alter this with total devolution from Westminster along the lines of what the Scots have. We are being failed at every turn. Every time you open a paper there is another report confirming this betrayal.

By Elephant

Related Articles

Sign up to receive the Place Daily Briefing

Join more than 13,000 property professionals and receive your free daily round-up of built environment news direct to your inbox

Subscribe

Join more than 13,000 property professionals and sign up to receive your free daily round-up of built environment news direct to your inbox.

By subscribing, you are agreeing to our Terms & Conditions and Privacy Policy.

"*" indicates required fields

Your Job Field*
Other regional Publications - select below