Lancashire cracks down on Cuadrilla
The county council has served an enforcement notice on the energy company, requiring the restoration of the Preston New Road fracking site in line with approved planning conditions.
Issuing of the notice follows a decision at LCC’s development control committee in December last year, which refused an application from Cuadrilla for a further extension of time to complete the site’s restoration.
Seeking to secure a cost-effective, domestic source of energy in shale gas to sell to the market, Cuadrilla pursued hydraulic fracturing – fracking – in Lancashire in the late 2010s, never without controversy, with opponents making the broad case that a technology much used in deserted stretches of countries such as the US and Australia was not safe enough in a built-up country like the UK due to the potential for instability.
A first consent was secured in 2016. In September 2018 the firm secured a consent for a second horizontal shale exploration well at Preston New Road in Little Plumpton, Fylde – its flagship site. Fracking took place through 2019 before things were called rapidly to a halt.
The government issued a moratorium in November of that year citing an Oil & Gas Authority report that concluded “it is not possible with current technology to accurately predict the probability of tremors associated with fracking”.
That moratorium was reimposed in 2022, and in 2023 Cuadrilla was granted an initial two-year extension for making good at the site.
In January 2025, the firm issued a press release setting out its plans to plug the exploration wells at PNR with cement, and remove surface pipework and valves – it then applied for a further extension to June 2027, which was refused in December in line with officer recommendation.
Sixty objections to the extension were recorded, and opposition groups such as Frack-Free Fylde were represented at the December meeting.
Since refusing Cuadrilla a time extension, LCC said that it has been informed that Cuadrilla will begin removing site infrastructure, marking the start of the restoration process.
However, the approved timetable for restoration was not met, “resulting in unacceptable and unnecessary harm to the rural character of the area”.
The enforcement notice requires all plant, buildings, security and acoustic fencing, pollution control membranes, aggregates and concrete hardstanding forming part of the drilling compound to be removed within four months of the notice being served. The land must then be restored to a condition suitable for agricultural use within six months of the notice being served.
LCC said it will not hesitate to take further action if the requirements of the notice are not met.
Cllr Joshua Roberts, cabinet member for rural affairs, environment and communities, said: “This situation has gone on for far too long. Local residents have had to live with this site for longer than they should have, and it is right that we have now taken firm action to bring this to a conclusion.
“It is positive that work is beginning to remove infrastructure from the site, but it is essential that the full restoration is completed within the required timeframe. We will not hesitate to take further steps if necessary.”
Cuadrilla has been approached for comment.